Totla Build Time - 18 Weeks.
Foundation (Weather Dependent) 2 Weeks
Framing (Weather dependent) 3 Weeks
Siding/roofing (Weather Dependent) 2 Weeks
Rough-In Electrical, Plumbing, HVAC 2 Weeks
Drywall Hang and Finish 2 Weeks
Prime and Paint Walls/Vinyl Floor Installation 1 Week
Trim Carpentry 2 Weeks
Final Wall Paint, Trim Out Electrical, Plumbing and HVAC 2 Weeks
Carpeting, Shelving, Mirrors and Punch List Items 2 Weeks