| Foundation (Weather Dependent) | 2 Weeks |
| Framing (Weather dependent) | 3 Weeks |
| Siding/roofing (Weather Dependent) | 2 Weeks |
| Rough-In Electrical, Plumbing, HVAC | 2 Weeks |
| Drywall Hang and Finish | 2 Weeks |
| Prime and Paint Walls/Vinyl Floor Installation | 1 Week |
| Trim Carpentry | 2 Weeks |
| Final Wall Paint, Trim Out Electrical, Plumbing and HVAC | 2 Weeks |
| Carpeting, Shelving, Mirrors and Punch List Items | 2 Weeks |